Alternergy unit seeks approval for P1.85-B connection facility

by
October 7, 2024
in Top News
0
Alternergy unit seeks approval for P1.85-B connection facility
0
SHARES
27
VIEWS
Share on FacebookShare on Twitter

THE SUBSIDIARY of Alternergy Holdings Corp. is seeking the approval of the Energy Regulatory Commission (ERC) to develop and operate a transmission facility to connect its wind power project in Quezon province to the Luzon grid.

Alabat Wind Power Corp. (AWPC) aims to construct dedicated point-to-point limited transmission facilities with a total estimated cost of P1.85 billion, the company said in its filing with the ERC.

The interconnection project will be undertaken by GEDI Construction Development Corp., the company said.

AWPC intends to negotiate with the National Grid Corp. of the Philippines (NGCP) regarding the operation and maintenance of the interconnection facility.

Based on the application, the company is proposing to build the Alabat Wind Power Project (AWPP) in Quezon province, which has a generating capacity of 49.9 megawatts (MW).

“The total generation output of the wind project will be limited to 49.9 MW so as not to overload the 69-kilovolt (kV) transmission line.”

The wind farm has an estimated project cost of P7 billion and is targeted for completion by November 2025.

In May, Alternergy announced the start of the construction of the AWPP with an installed capacity of 64 MW.

AWPC is proposing to connect the interconnection facility to the Luzon grid through a tapping point or switching station along the NGCP’s Gumaca-Lopez-Tagkawayan 69-kV transmission line.

“The construction of the Interconnection Project is a prerequisite for the testing and commissioning, and ultimately, the commercial operations of the AWPP. A provisional authority is, thus, urgently needed to enable AWPP to achieve the target COD (commercial operations date) and avoid adverse consequences to AWPC,” the company said.

Alternergy is targeting to increase its renewable energy capacity to 500 MW by 2026.

At the local bourse on Monday, shares in the company rose by 2.3% to close at P0.89 apiece. — Sheldeen Joy Talavera

ShareTweetPin

Related Posts

Have a taste of the perfect day in paradise with SULÀ Spirits
Top News

Have a taste of the perfect day in paradise with SULÀ Spirits

January 8, 2025
First months of 2025 likely rainy amid La Niña conditions, says PAGASA
Top News

First months of 2025 likely rainy amid La Niña conditions, says PAGASA

January 8, 2025
December inflation rises to 2.9%
Top News

December inflation rises to 2.9%

January 7, 2025
Outstanding debt hits fresh high of P16.09T
Top News

Outstanding debt hits fresh high of P16.09T

January 7, 2025
Outstanding debt hits fresh high of P16.09T
Top News

Outstanding debt hits fresh high of P16.09T

January 7, 2025
PHL end-December dollar reserves drop to $106.8B
Top News

PHL end-December dollar reserves drop to $106.8B

January 7, 2025
Next Post
T-bill rates rise as bets of big Fed cut fade

T-bill rates rise as bets of big Fed cut fade

Recommended

The 2024 IMF-World Bank meetings and their recommendations for Asia: An assessment

The 2024 IMF-World Bank meetings and their recommendations for Asia: An assessment

November 14, 2024
4 Factors That Drive Silver Demand

4 Factors That Drive Silver Demand

December 5, 2025
Fiscal, monetary tools limited for spurring ASEAN economies — ANZ

Fiscal, monetary tools limited for spurring ASEAN economies — ANZ

January 6, 2025
Senate to boost defense budget next year amid growing tensions with China

Senate to boost defense budget next year amid growing tensions with China

August 22, 2024
Planters Products, Inc. to hold Annual Stockholders’ Meeting on Dec. 5 via Zoom

Planters Products, Inc. to hold Annual Stockholders’ Meeting on Dec. 5 via Zoom

November 3, 2024
English Heritage’s Bolsover Castle Offers BWY Yoga Classes

English Heritage’s Bolsover Castle Offers BWY Yoga Classes

September 12, 2024

    Become a VIP member by signing up for our newsletter. Enjoy exclusive content, early access to sales, and special offers just for you! As a VIP, you'll receive personalized updates, loyalty rewards, and invitations to private events. Elevate your experience and join our exclusive community today!


    By opting in you agree to receive emails from us and our affiliates. Your information is secure and your privacy is protected.

    Prince Silver

    Prince Silver

    March 11, 2026
    Questcorp Mining Completes Induced Polarization Survey at the Marisa Zone – North Island Copper Project

    Questcorp Mining Completes Induced Polarization Survey at the Marisa Zone – North Island Copper Project

    March 11, 2026
    Byron King: Gold, Silver, Oil/Gas — Stock Ideas and Strategy Now

    Byron King: Gold, Silver, Oil/Gas — Stock Ideas and Strategy Now

    March 10, 2026
    • Privacy Policy
    • Terms & Conditions

    Copyright © 2026 investdailypro.com | All Rights Reserved

    No Result
    View All Result
    • Home
    • Privacy Policy
    • Suspicious engagement
    • Terms & Conditions
    • Thank you

    Copyright © 2026 investdailypro.com | All Rights Reserved